As of today the plumbing is roughed in, the hot water heater is installed, and the sewer and water connections are complete.
The electrician should be in next week, and we have purchased the Heating/AC unit and the toilet. Pretty soon we will enlarge the doorways, get started on the rest of the framing, and pretty soon this remodeled handicap accessible bathroom will be a reality.
Praise the Lord for our new bathroom, which is greatly needed, and for all the individuals who thought of it and helped make it real. May the Lord bless you all.
Today the new electrical panel and associated wiring was installed. Progress continues at a good pace.
Thanks to Charles Chavez and crew of Courtesy Plumbiing and Luis Maldonado and staff of ADO Electrical for their professional work.
Well I thank God for you brothers and sisters and leaders, for God works all things together for good to those who love Him and are called according to His purpose. God has put a small and faithful group together, and our hermana Iglesia Sinai que Dios los bendiga.
Today was interesting. I thought that I was going to meet a framer so as to show him what needed to be done, but Candio showed up with his tools and we got most of it done today.
Now to start wiring and insulating so that we can begin the sheetrock.
Update 8/28:
Ceiling rafters are in, electrical wiring done. Ready to set the shower walls, insulate, and then sheetrock. Making progress.
Thanks to Allen McGarr for all the hard work.